Uzbekistan Bash Wind Farm Turbine Maintenance Project

This turbine maintenance project commenced on June 13, 2025 and was completed on June 22, 2025. It involved turbine maintenance work at the Bash Wind Farm in Bukhara Region, Uzbekistan. The turbines have a hub height of 100 meters, with each rotor assembly weighing approximately 108 tons.

To ensure safe and efficient operations, we deployed one 800-ton crawler crane and one 900-ton crawler crane working in tandem for the disassembly and reinstallation of turbine components.

The main maintenance tasks included: Dismantling slip rings, slip ring cables, and other accessories; Manual pitch adjustment and fixation of blades; Dismantling the rotor and installing blade tip covers; Blade cutting and replacement. 